The 2017 FIDIC Contracts. William Godwin

Чтение книги онлайн.

Читать онлайн книгу The 2017 FIDIC Contracts - William Godwin страница 11

The 2017 FIDIC Contracts - William Godwin

Скачать книгу

at his own risk and cost any works resulting from improper operation or maintenance attributable to matters for which he is responsible under clauses 5.5–5.7 – that is, training (to the extent specified in the Employer's Requirements), provision of as‐built documents and operation and maintenance manuals – or otherwise.)

      1.4.2 Employer Risks

       Liability for care of the works and indemnities

       Extensions of time

      In all three of the 2017 Books the Contractor's entitlement to claim an extension of time has been increased.

       (a) Access routesThe 1999 Books all provide for the Contractor to bear the costs of any non‐suitability or non‐availability of access routes for the use required by the Contractor without apparent qualification. If an access route were, for example, altered by the Employer or those for whom he was responsible, including his other contractors on site, the Contractor might be able to rely on clause 8.4(e) to claim an extension of time if he suffered delay as a result, on the basis that the alteration of the route was a delay, impediment or prevention caused by or attributable to the Employer, his personnel or his other contractors on site; but if the route were altered by a third party the Contractor would not be able to come within this ground and clause 4.15 would not appear to give him any basis for claiming an extension either.The Contractor's position has been improved by clause 4.15 of the 2017 Books, which provides (in the last paragraph of clause 4.15) that to the extent that non‐suitability or non‐availability of an access route arises as a result of changes to the access route by a third party, as well as the Employer, after the Base Date and they result in delay and/or cost the Contractor may claim an extension of time and/or payment of that cost. This fills an important gap in the 1999 forms.

       (b) Private utilitiesThe Contractor under the 2017 Books is now able to claim an extension of time in respect of delays caused not only by public authorities but also private utilities in the country of the project under a new clause 8.6. In the 1999 contracts clause 8.5 permitted a claim only in respect of delays caused by public authorities. This updates the earlier forms to reflect the fact that many utilities are now provided by private entities and represents a significant addition to the Contractor's right to claim.

       (c) Shortages in Employer‐supplied materialsThe Contractor may in all three 2017 Books claim an extension of time in respect of unforeseeable shortages in the availability of Employer‐supplied materials, as well as personnel or goods, caused by epidemic or government actions (clauses 8.5(d) 2017 Red and Yellow Books and 8.5(c) Silver). In the 1999 editions of the Red and Yellow Books the Contractor (by clause 8.4(d)) is only able to claim for unforeseeable shortages in personnel or goods caused by epidemic or government actions and in the 1999 Silver Book this ground is not available at all. The 2017 editions have therefore created an entirely new basis of claim for the Silver Book Contractor and increased the scope of the existing sub‐paragraph (d) of clause 8.4 in the other two Books by including Employer‐supplied materials.

       Latent defects in plant

      The 1999 contracts provide for defects which become apparent after the Employer's acceptance of the works (by issue of the Performance Certificate) by treating each party as remaining liable for the fulfilment of any unperformed obligations at that time, the Contract to be deemed to remain in force for the purpose of determining the nature and extent of such unperformed obligations (clause 11.10). There is no time limit placed on the extent of this liability; that question depends on the governing law.

       Termination for convenience and omitted work

      One of the complaints contractors make about the 1999 Books is that, in the event of the Employer's terminating the Contract for his own convenience, that is, in the absence of any fault on the part of the Contractor, the Contractor is not entitled to any loss of profit suffered as a result. Instead, clause 15.5 gives the Contractor no more than he would be entitled to where there has been a termination by reason of force majeure.

       Change in laws

Скачать книгу