Maintaining Mission Critical Systems in a 24/7 Environment. Peter M. Curtis

Чтение книги онлайн.

Читать онлайн книгу Maintaining Mission Critical Systems in a 24/7 Environment - Peter M. Curtis страница 20

Автор:
Жанр:
Серия:
Издательство:
Maintaining Mission Critical Systems in a 24/7 Environment - Peter M. Curtis

Скачать книгу

Escalation Procedures is to allow for the successful response to a critical site event. Following the escalation process, assures proper notification and timely response. By assessing the event first, critical information will be available early on. It is important that a chain of command be followed because when events arise, teams need to ensure that communication and reactions are escalated in the proper fashion.

      A summary of the phases given in ASHRAE appears below, with some additions for mission critical facilities. These additions, along with all phases, should be included in all mission critical facility projects.

       Pre‐Design phaseDocument Owner’s project requirements and basis of design

       Design phaseCommission focused Design reviewWriting Cx specifications

       Construction phaseFactory Acceptance Testing ‐ FATConstruction check listingStart‐up (Pre‐functional) testing

       Acceptance phaseSite acceptance (Functional)Acceptance testing to verify the performance of critical equipmentIntegrated testingO & M document reviewStaff training oversightDevelop and prove out EOPs. SOPs and MOPs

       Occupancy and Operations phaseContinual review and updating of materialsContinual training of O&M staffReliability Assurance Testing (continual commissioning)

      In the design phase, we have a commissioning‐focused design review that should not be confused with a peer review. In a commissioning‐focused design review, the commissioning engineers should provide input on making the building and systems easier to commission and easier to maintain. They should also examine equipment layout, labeling schemes, and other ergonomic factors, which can result in a facility that operations team members find intuitively easy to work with. This, in turn, reduces the likelihood of operator error in emergency response situations. The CxA should also verify that bid documents adequately specify building commissioning as this will help reduce vendor change orders. It many cases it is better to have the CxA provide commissioning specifications and have them included in the pre‐purchase and other bid sets. The focused review also needs to verify that there are adequate monitoring and control points specified to facilitate commissioning and O&M (trending capabilities, test ports, control points, gages, and thermometers). A review needs to include a review of design as it pertains to the reliability and redundancy standards of the owner and industry standards and verifies that building O&M plan and documentation requirements specified are adequate.

      During the construction phase, much of the rudimentary testing is accomplished. During this time, the factory acceptance testing is being conducted, and it is important to have the CxA involved to verify that the controls and interlocks will work with the complete system. During this time, equipment is being delivered and installed. During this installation, the vendors and GC should be verifying the installation using construction checklists provided by the CxA. These checklists basically track the construction process and verify that the vendor delivered what was paid for in good condition, installed properly, and has the proper clearance. The vendor startup will follow, and if performed in accordance with the agreed procedures, all the functions, including all the alarms, will be verified. It is important to track all these documents and have them signed off by the vendors as proof of proper startup. In some cases, the vendors will sign off the documents and not perform all the requirements, and that will slow down the acceptance and integrated testing. In this case of improper start‐up, the delays can be back charged to the responsible vendor.

      1 Emergency power systems and controls.

      2 Uninterruptible power supply (UPS) systems and batteries.

      3 Flywheel energy storage systems.

      4 Static Transfer Switches (STS) and all associated controls.

      If the acceptance testing is done properly, it should, at a minimum, verify the equipment is worthy of critical load. In some cases, deficiencies found during this process have forced the vendors to meet their own specifications and improve product quality.

      We are now ready for integrated testing, and the intent of this test is to verify that the building and all the systems work together to meet the client’s design requirements. Some hints for having a successful integrated test that proves proper operation and no unwanted system interaction are:

      1 Perform a full data center heat load test, including any enclosed cooling systems.

      2 Perform integrated testing at 25%, 50%, 75%, and 100% of the design load.

      3 Use data loggers on the data center floor to verify measured data and BMS controls.

      4 Check all operating modes, including maintenance configurations.

      Staff training and operations documents need to be provided before we can start operations. Proper training must be given to the staff for systems and integrated operations. I would suggest that the vendors provide system training,

Скачать книгу