       What can you do to prevent the problem from happening again?

       How will the solution be implemented?

       Who will be responsible for it?

       What are the risks of implementing the solution?

      A short list of potential corrective action are generated. Each potential corrective action should be carefully scrutinized to determine if it actually will correct the problem. Because many time the analyst Try to fix the symptoms of problems rather than the true root cause. Therefore, care should be taken to evaluate each potential corrective action so that the right one can be implemented to eliminates the real problem. Many a time all corrective actions are not financially justifiable. In some cases, the impact of the incident or event is lower than the cost of the corrective action. In these cases, the RCA should document the incident for future reference, but recommend that no corrective action be taken on some occasions, implementing a temporary solution is the only financially justifiable course of action which can only correct the symptoms. In these instances, the recommendation should clearly define the reason the limitations why this decision was taken and what impact it will have on plant performance.

      Also, consider whether the changes you plan to make will impact other areas of your business. Changes to processes can have knock‐on effects. Be sure you aren’t setting yourself up for a new set of problems when you implement the solution. To do this, you need to look at your process flows and how they relate to one another.

      The final part of the solution design process is to decide on checks and balances that will tell you whether your business is implementing the solution you’ve devised and whether it works as planned.

      Implementation means change, and change must be carefully managed. Everyone concerned needs to know about your solution and the reasoning that led you to believe that you can solve the problem.

      So, explain the root cause analysis process and how you arrived at your conclusion. Explain your solution and how you want it to be implemented. Ensure that everyone involved has the knowledge and resources they need to follow through and devise method for testing your new system.

      Keep in mind, though, that it’s always better to first apply the solution on a small scale. You can never know what could go wrong. Once you’re certain that the new solution brings results, you can start applying it company‐wide.

      When you designed the solution, you decided on key indicators that would allow you to see whether the solution works. Use these indicators to follow up. In this instance, you’re going to see whether the symptoms are gone. The presence or absence of the issues that launched you on your root cause analysis and problem‐solving initiative will tell you whether you have successfully solved the problem. Remember to watch out for new issues that may arise elsewhere as a result of the changes you made.

      Everyone can make errors no matter what their level of skill, experience or how well trained and motivated they are. Commonly cited statistics claim that human error is responsible for anywhere between 70 and 100% of failure. Many major failures, e.g. Texas City, Piper Alpha, Chernobyl were contributed by human failure. To enhance reliability, companies need to manage human failure as robustly as they manage technical and engineering failures. It is important to be aware that human failure is not random; understanding why errors occur and the different factors which make them worse will help you develop more effective controls.

      Human error was a factor in many highly publicized accidents in recent memory. The costs in terms of human life and money are high. Placing emphasis on reducing human error may help to reduce these costs. This chapter provides an insight view about the causes of human errors and suggests the way to reduce the errors.

      Table 4.1 illustrates how the failure of people at many levels within an organization can contribute to a major disaster. For many of these major accidents, the human failure was not the sole cause but one of a number of causes, including technical and organizational failures, which led to the final outcome. Remember that many “everyday” minor accidents and near misses also involve human failures. All major disasters lead to huge human, property, and environmental losses.

      All this evidence shows that human error is a major cause of unreliability or causation of accidents.

      What Types of Errors Do Humans Make?

Accident, industry and date consequences Human contribution and other cause
Union Carbide Bhopal, 1984 (Chemical Unit) The plant released a cloud of toxic methyl isocyanate. Death toll was 2500 and over one quarter of the city's population was affected by the gas. The leak was caused by a discharge of water into a storage tank. This was the result of a combination of operator error, poor maintenance, failed safety systems, and poor safety management.
Space Shuttle Challenger 1986 (Aerospace) An explosion shortly after lift‐off killed all seven astronauts on board An O‐ring seal on one of the solid rocket boosters split after take‐off releasing a jet of ignited fuel. Inadequate response to internal warnings about the faulty seal design. Decision taken to go for launch in very cold temperature despite faulty seal. Decision‐making result of conflicting scheduling/safety goals, mindset, and effects of fatigue.
Piper Alpha 1988 (Offshore) 167 workers died in the North Sea after a major explosion and fire on an offshore platform Formal inquiry found a number of technical and organizational failures. Maintenance error that eventually led to the leak was the result of inexperience, poor maintenance procedures, and poor learning by the organization. There was a breakdown in communications and the permit‐to work system at shift changeover, and safety procedures were not practiced sufficiently
Texaco Refinery, 1994 (Petroleum Industry An explosion on the site was followed by a major hydrocarbon fire and a number of secondary fires. There was severe damage to process plant, buildings and storage tanks. 26 people sustained injuries, none serious. The incident was caused by inflammable hydrocarbon liquid being continuously pumped into a process vessel that had its outlet closed. This was the result of a